I-96, Wacousta Road to M-43 (Saginaw Highway) This two-year project involves the reconstruction of I-96 from Wacousta Rd. to M-43 (Saginaw Hwy.), reconstruction of the I-96 interchange ramps at Grand River Avenue and M-43, reconstruction of the M-43 and Canal Road intersection, and rehabilitation of ten bridges along I-96.
Mainline I-96
Work is currently scheduled to
start the week of March 8th, weather permitting. At this time night time double
lane closures on Westbound I-96 will be used to place traffic control which will
shift Westbound I-96 traffic to the outside shoulder and outer most lane.
The 3 lane sections will be reduced to a 2 lane section.
Concrete barrier wall, will then be placed to allow Eastbound traffic to be
crossed over onto the Westbound inside shoulder and inside lane.
There will be 2 lanes in Eastbound and Westbound directions on I-96 once traffic
control is fully implemented, and work will progress during the day time hours.
Once Eastbound traffic is shifted to the Westbound lanes, Eastbound traffic will
have access to all open ramps via the use of crossovers that were constructed in
the fall of 2009.
This traffic configuration is expected to be in place until approximately the
middle of July.
M-43 Ramps
During the first stage of construction, all ramp movements
will be maintained using the existing ramps as well as the temporary ramps
constructed in the fall of 2009.
Entrance ramps to I-96 will be under a yield condition during the night time
lane closures.
Temporary signals will be placed at the temporary ramps to facilitate the
traffic movements required.
Alternate ramp access for this stage of construction are as follows:
The ramp from M-43 Eastbound to I-96 Westbound will use
the ramp from M-43 Westbound to I-96 Westbound.
The ramp from I-96 Eastbound to M-43 Eastbound will use the ramp from I-96 Eastbound to M-43 Westbound.
The ramp from I-96 Westbound to M-43 Westbound will use the ramp from I-96 Westbound to M-43 Eastbound.
Grand River Ave Ramps
All ramp movements for the Westbound I-96 traffic will be
maintained in this stage of Construction.
Entrance ramps to I-96 will be under a yield condition during the night time
lane closures.
During this stage of Construction the ramps for Eastbound I-96 exiting at Grand
River as well as the entrance ramp to Eastbound I-96 will be detoured for 18
calendar days each.
Only one ramp closure will be allowed at a time.
There will be further notifications 10 calendar days prior to these detours
being established.
Detour routes for these ramps will utilize the M-100/Wright Rd exit and Grand
River Ave.
I-69 Ramps
Access will be maintained at all times to all ramps in
this stage of construction.
Work will be starting on March 8th on the bridge ramp from Westbound I-69 to
Eastbound I-96. This two lane ramp will have a single lane closure with a
traffic shift.
Ramps from I-69 to I-96 will be under a yield condition during the night time
lane closures.
M-43 Canal to Marketplace
M-43 will be reconstructed from Canal to Marketplace with
all work scheduled to take place in 2011.
You may experience minimal intermittent night time shoulder and lane closures on
M-43 for bridge work at the I-96 interchange during the 2010 construction
season.
Construction schedules are subject to change, based on contractor's decisions
and weather. MDOT will let you know of any major changes or updates through this
e-mail alert feature.